ENVIRONMENTAL IMPACT STUDY FOR SUNLIGHT ENTERPRISES
The next study was made for Sunlight Energy Enterprises and it was
conducted to meet the possible demands of the government in the approval
process, it is expected that investment guarantees should be extended to ensure
fair and reciprocal investment gain is achieved. The simple truth is that
without an environmental study we could never expect approval.
After analyzing carefully the economic circumstances of the collapse
of the global economy in 2008 we had formulated this analysis. We must be aware
of the interventionist policies of the government of Ecuador and the lack of
reliable laws, we must also take in consideration the lack of an independent
Supreme Court that it is practically incapable of taking decisions in
accordance with the law, but rather to the political whim of its members. At
the same time extremely high tariffs (up to 40%) makes solar and wind systems
extremely expensive and very few if any incentives are offered by the
government of Ecuador.
All projects must be approved before presenting the results of the
financial and economic evaluation to establish an analysis to indicate whether
the projects have a high probability of being economically and financially
feasible ; Apart from being able to consider the serious impacts on
environmental resources in the area also to avoid causing large losses in the
economic welfare of the communities in the province and all citizens living in
the vicinity of the geothermal Chachimbiro complex where several rivers are
born. We estimate that our company will build and operate a unique hybrid power
plant in the world could gain around 97 million in net present value terms
annually.
This figure is the sum of the profits of each year, which are
discounted using an interest rate which reflects potential income from other
investments and the cost of credit to indicate an investment is feasible.
We translate the financial value to an economic figure for a
broader approach, considering the costs and benefits for Ecuador as a whole and
not just for the investor. This conversion makes the analysis excluding any
taxes or subsidies, which are artificial transfer mechanisms introduced by the
State, using shadow prices, which correct deficiencies in the structure of
markets for inputs and outputs of the project. Finally external shocks, defined
as those forgone by the company financially, but clearly assignable to
activities included.
The economic net present value of the project was estimated at 92
million: 40 million for geothermal production, 15 million for solar production,
22 million for wind energy production. This last result masks the fact that the
negative impacts of the project are concentrated in an environment of global importance
for conservation, and social sector traditionally abandoned and disadvantaged.
There is a need to establish very clearly the demarcation of the
park Cayapas- Cotacachi to avoid damage either in deforestation due to the
creation of new access roads near their limits, and the possibility that
migratory birds could affect some areas. If biodiversity is affected choco
Ecuador, it is likely that impacts will spread to other ecosystems, as its
geographical location, serves as a bridge for the exchange of fauna between the
Colombian and Ecuadorian region choco and with them the rest South America
Complex Cotacachi Cayapas- shaped central part is one of the
regions of the planet with greater endemism and biodiversity. Due to lack of
reliable data, this study does not estimate a monetary value for any losses in
biodiversity, and calculates the additional costs of monitoring and management
of protected forest. However, as an integral support to remedy nature Sunlight
Energy Enterprises Inc , proposes voluntarily make planting five million trees
in the next five years throughout the area comprising the Chachimbiro
geothermal complex. Creating a positive both biodiversity and environmental
impact. We stuck to an estimated gross cost of carbon dioxide emissions and the
cost of a rescue attempt of birds and animals that could be affected by the
project. The first value is 13 million, while the second was estimated
24millones. Apart from the environmental impacts would be the socio-cultural
communities between Urcuqui and Pablo Arenas.
These communities must be given opportunities to work on projects
and therefore training and employment opportunities should be offered. If the
project is approved by the national government and local governments, these
communities shall not be isolated and we should work hard so that we can
minimize any damage to natural resources. Rather, we should strive to provide
work in building roads and work that will serve as a positive impact in their
communities, working together and in consultation with leaders of these
communities. Besides that the company will voluntarily make donations to
schools, colleges, universities in the province to encourage education and
social welfare. Considering the case, it is not possible to reduce to a monetary
figure the effects on common history and traditions that would be affected by
the works and opening of access roads. Therefore, this analysis is intended
only to glimpse the uses that communities make of natural resources and the
increase in the cost of living that involves the comprehensive development of
the Province. In the case of the area of the city Yachay proposal we firmly
believe that the government should provide compensation to the communities of
El Puente, San Antonio, Tapiapamba, Las Mercedes, Tola and San Vicente.
According to our calculations, these communities will suffer losses that could
reach 56.2 million. This is a clear case in which an economically efficient
investment will not be fair. The analysis in a projection of similar situations
in other countries it should be noted that the benefits of creating a knowledge
city and an industrial area would receive Yachay private company, the lending
banks and the government , while the costs communities would bear the Province
of Imbabura
It is recommended that the municipalities of the Province obtain
an independent study of the true economic impact that will be caused by the
creation of a city that it is certainly much more than a university and
industrial complex, there is no question that tourism will also be affected and
especially here requires at least five years in the medium-term and probably
about twenty years of development that will require constant subsidies from the
government that may cause the abandonment of the other cities. It is therefore
important that there is a contract or formal commitment of the government with
Sunlight Energy Enterprises of the
distribution of costs and benefits.
In theory, this non- equitable distribution of costs and benefits
can be corrected through compensation to institutions. In practice,
compensation and environmental measures are often insufficient in the context
of major infrastructure projects. Environmental Impact Studies that were
conducted by Sunlight Enterprises Inc. only with the opportunity to present the
project to create a hybrid plant geothermal, solar, and hydro and wind in the
Province of Imbabura did not consider more than the creation of a small
university complex with the planning and investment of Universities like
Oxford, MIT. UVA and George Mason. We never considered such a huge complex of
University City, City of Tourism and Industrial city as it is being proposed
with Yachay. Therefore, we do suggest that spending on social compensation and
environmental protection will reduce the impacts that we have calculated in
this study, which, in any case, are only estimates of partial damage. However,
following the preliminary study and a computerized calculation it is estimated
that if Sunlight Energy Enterprises participates in creating a production of at
least 200MW hydro and wind, the Province may receive at least 87 million in
profits. Yachay on the other hand in the current form since it requires
subsidies from the central government and tax incentives to the Corean Company
it will be pretty costly to the Province. We have a projection that indicates
that the losses to expect in loss of businesses and damages to the economy of
the Province will be around 95 million.
In other words the construction of a power plant with the capacity and
design and has been patented by Sunlight Energy Enterprises becomes important
as their contribution payments in local and provincial taxes will be
significant to compensate and mitigate the impacts of Yachay .
Finally, we must recognize that any work of this magnitude brings
impacts on the environment and culture that cannot be avoided or mitigated. It
is up to the Ecuadorian society, mainly citizens of Imbabura to decide if the
benefits of energy for domestic and export consumption are important enough to
justify these sacrifices. Our study was conducted considering the proposed
plant to the government of Ecuador. Our estimates do not consider the
environmental impact of college Yachay industrial Yachay . tourist Yachay
PS. We have withheld some figures and certain full details. I left
some figures for illustration and that this study is not used for other
purposes.
Computer analysis: Economic projection:
Government Income Population Nature Company Bank loss
Energy sales (5% sales) 27 , 739
Taxes construction investment Generation Costs March 07 -8.883
Sales and administrative expenses -906
Tax (30 % income) 75 084 Increase in unrealized loss monitoring
costs
Removing forest cover -24.896
Modifications aquatic fauna , wildlife -1.335
Fragile areas (biodiversity, loss not
Climatological factors ) quantified
Changes -56.202 living conditions
Changes indigenous culture , mixed culture , unquantified loss
Changes in health and education -
Total Impact on Sector 95 million lost Rates comunidades-B/.56 , 202
-B / . P 26.23
Possible tax payments locales.87, 957 Gross Value
DISTRIBUTION OF INCOME FOR SEE INC
CONSTANT PRICES AND CASH DISCOUNTED )
Legal environment
• Adoption of Local Government and central Ecuador is in the
process.
• Permits: All necessary permits will be obtained as required
under
• Sunlight will comply with all environmental work requirements,
and all other regulations of the country.
• Agreements: A special agreement with the central government of
Ecuador regarding the guarantee of investment must be part of the same
agreement to invest in Ecuador. A minimum of thirty -year warranty on the
ownership and management of the Company or otherwise compensated.
• Requirements zoning and construction laws. Sunlight plans to
build using the highest industry standards in both construction and in all
buildings.
• Insurance Coverage. It is important to get insurance in all
aspects of the construction
• Trademarks, copyrights, or patents
(pending, existing, or Purchased ) A full list of patents, Copyright and
Trademarks will be documented.
The Future:
When we initiated the plan in 2007 we
analyzed all the circumstances. The biggest challenger is actually not to be
able to count with the scientific personnel that is needed to run an enterprise
of such magnitude. Therefore we had laid out what the ideal University should
be. It is the intention of Sunlight Energy Enterprises to devote at least 15%
of earning to the development of a scientific University unlike no other. The
great difference will be that every single student will be required to “be
hands on” in all the projects. Every year students will be required to
participate in helping build, repair, and work on all the projects of the
University and we are hopeful that we could engage American Universities in
these endeavor.
We are looking into the future and as
such we have designed several building, structures and sevral inventions to
improve and build better structures in architecture, and in our development:
No hay comentarios:
Publicar un comentario